Severn Trent Water Limited – AMP8 Cresswell Cryptosporidium and Pathogens
Notice under regulation 28(4) of the Water Supply (Water Quality) Regulations 2016 (as amended)
Reference: SVT-2023-00008
Version Number: 1
Water undertaker as appointed under section 6 of the Water Industry Act 1991 (as amended): Severn Trent Water Limited, with registered number 02366686 (hereinafter called ‘the Company’).
Assets Affected:
Asset Name |
Reference |
---|---|
Cresswell Borehole Pumping Station (BPS) |
T0044 |
Water Accountability Zones: Leek, Stoke and Hanchurch |
ST04, ST03 and ST02 |
Supply Systems |
YST02, YST03, YST03/ST04, YST04 |
Details of this Notice:
- The Drinking Water Inspectorate (‘the Inspectorate’) has received a regulation 28(1) report of the Water Supply (Water Quality) Regulations 2016 (as amended) (‘the Regulations’) from the Company dated 22 September 2023, which states that there is or has been a significant risk of supplying water from Cresswell BPS (and associated assets as applicable) that could constitute a potential danger to human health or could be unwholesome.
- Consequently, this Notice is served on the Company by the Inspectorate on behalf of the Secretary of State, under regulation 28(4) for the assets listed above, for risks associated with:
Description of Risk |
Hazard/ Hazardous Event/ Parameter |
Hazard I D |
---|---|---|
Deterioration of raw water source |
Cryptosporidium |
T0044-254-T-C111-C111-24U |
Deterioration of raw water source |
E. coli |
T0044-254-T-H035-C002-23Q |
Deterioration of raw water source |
Enterococci |
T0044-254-T-H035-C003-2Q2 |
Deterioration of raw water source |
Coliforms |
T0044-254-T-H035-C001-23P |
- The Company are required to satisfy the following requirements.
The date given is that until or by which the requirements must be maintained or satisfied, as appropriate.
Requirements:
(a) To maintain the following measures for the period specified in each case:
- Continuous real time online turbidity and chlorine monitoring
Date: Ongoing for the duration of this Notice - Weekly monitoring of raw and final water for bacteriological parameters and Cryptosporidium. Continuous monitoring of Cryptosporidium on the final water and four times per week for bacteriological parameters.
Date: Ongoing for the duration of this Notice - Continue to optimise existing treatment systems.
Date: Ongoing for the duration of this Notice - Maintain catchment surveillance and make interventions to mitigate potential contamination.
Date: Ongoing for the duration of this Notice
(b) To review, revise or make operational the following measures, by the dates specified in each case:
- Review and confirm the appropriateness of the proposed solution to provide Ultraviolet (UV) disinfection to secure or facilitate compliance with statutory requirements.
Date: 30 September 2027 - Complete outline design and determine expected start date for construction of the agreed solution.
Date: 30 September 2028 - Commence construction of UV solution and confirm expected completion date.
Date: 31 March 2029 - Complete construction and commissioning of the agreed solution.
Date: 31 March 2030
(c) To audit whether the measures have been effective by the following means:
- Define an audit strategy to monitor the effectiveness of the measures specified in sections (a) and (b).
Date: 31 March 2024 - Implement, and keep under continuous review, the audit strategy defined in measure (c)1.
Date: Following completion of measure (c)1. onwards.
(d) Not to supply water for regulation 4(1) purposes from Cresswell BPS, or not to so supply unless the specified conditions below are satisfied:
- Not applicable
(e) To provide the following information in the time and manner specified below to enable monitoring of progress towards the mitigation of the risks:
- Provide a progress report annually.
Date: by 31 January each year. - Confirmation of the appropriateness of the proposed solution and details of the strategy for auditing the effectiveness of the measures to be made operational.
Date: 31 October 2027 - Confirm completion of outline design and expected start date for construction of the proposed solution.
Date: 31 October 2028 - Confirm commencement of construction and expected completion date.
Date: 30 April 2029 - Confirm completion of construction and commissioning of the agreed solution
Date: 30 April 2030 - Submit the audit strategy for auditing the effectiveness of the measures, as specified in measure (c)1.
Date: 30 April 2024 - Submit any revisions of the audit strategy produced under measure (c)2.
Date: Within 1 month of a revision - Submit a report in the event that any completed measures of this Notice need to be altered in any way, for any reason.
Date: Ongoing for the duration of this Notice - Submit a satisfactory completion report accompanied by a revised regulation 28(1) report with Board level Director sign-off.
Date: 30 April 2031
Further Details of this Notice:
- Any product or substance used as a result of the requirements in this Notice must comply with regulation 31.
- Under regulation 28(6) the Inspectorate, on behalf of the Secretary of State, may by notice served on the Company, revoke or vary this Notice.
- Failure by the Company to comply with this Notice may result in enforcement proceedings under section 18 of the Water Industry Act 1991 (as amended).
Signed
Nicholas Adjei
Deputy Chief Inspector, on behalf of the Secretary of State for Environment, Food and Rural Affairs
31 January 2024
Reference: SVT-2023-00008